CAUAYAN CITY – NATAPOS NA ANG FLOOD CONTROL PROJECT SA KAHABAAN NG ILOG PINACANAUAN SA BENITO SOLIVEN, ISABELA, NA LAYONG PROTEKTAHAN ANG MGA RESIDENTE NG BARANGAY YEBAN SUR AT MALUNO NORTE MULA SA MATINDING PAGBAHA.
ISINAGAWA ITO NG DPWH-ISABELA 3RD DISTRICT ENGINEERING OFFICE GAMIT ANG GABION WORKS NA MAY FILTER CLOTH—MGA ISTRUKTURANG GAWA SA BAKAL AT BATO NA DINISENYONG PIGILAN ANG PAGGUHO NG LUPA AT KONTROLIN ANG DALOY NG TUBIG.
ANG PROYEKTO AY MAY KABUUANG HABA NA 736 METRO, NA HINATI SA DALAWANG BAHAGI: 246 METRO SA SECTION 1 AT 490 METRO SA SECTION 2.
SA HALAGANG ₱96.4 MILYON MULA SA GENERAL APPROPRIATIONS ACT 2024, MAKIKINABANG DITO ANG MGA KOMUNIDAD SA PALIGID NG ILOG NA MATAGAL NANG BINABAHA, SA LAYUNING MAPROTEKTAHAN ANG KANILANG KABUHAYAN AT KALIGTASAN.